PSE SA - More than 100 MWh delivered. Stabilisation of the network. - Lerta

PSE SA – More than 100 MWh delivered. Stabilisation of the network.

Network stabilisation. Control room at the power station

Stabilisation of the electricity grid.

As the third largest DSR aggregator in Poland, Lerta is often called upon by PSE (Transmission System Operator) to supply energy from aggregated units to the grid. Since the launch of the Capacity Market in 2021. Lerta has been called upon 10 times so far, delivering 62 MWh, often during peak hours, helping the TSO to maintain grid stability.

 

Key numbers:

Project Details

0

calls for reduction of energy consumption from the grid

0 MWh

energy was delivered at the request of TSO

0 mln EUR

paid to Lerta by Polish TSO (PSE)